How do I transfer a POD between projects?

To transfer a POD between projects you need to have access to the admin dashboard, iotile.cloud
Note that for POD-1Ms, the projects have to be set up correctly for POD-1Ms otherwise, the POD-1Ms cannot be used correctly.

It is advised that trips be finished and archived correctly before PODs are transferred between projects.

  1. Log in to iotile.cloud
  2. Click on the project that the POD currently sits in

  3. Click on the ID of the POD you want to transfer

  4. Confirm that the POD ID is correct

  5. Click on 'Move to different Project'

  6. Select the project you want to move the POD to

  7. If you have an active trip that you want to move mid-trip to a new project and want to not lose the data, select on 'Move data'. Otherwise, unselect.

  8. Click on 'Submit'

  9. Once the transfer is complete, you will receive an email. Now the POD will be part of the new project.

Still need help? Contact Us Contact Us